Location : Brgys. Sta. Cruz, Brgy. Tingib & Brgy. Guia, Pandan, Antique
No. of Units : 3 Resettlement Sites; 3,497 Housing Units
Project Name : Construction of Water Supply System for NHA Yolanda Permanent Housing Project
Fund Allocation : Php 22,185,146.00
Status : Completed
The newly constructed 256 cubic meter concrete ground reservoir to distribute safe water to NHA Housing Sites. Beside the newly constructed reservoir is the old/existing reservoir of the Pandan WD.

Inspection of pipelaying along the national highway to provide safe and potable water to the NHA Housing Sites.

 The inauguration of water supply system on November 19, 2018 attended by LWUA Acting Administrator Jeci A. Lapus, Pandan WD BODs/GM, PWD/LWUA Staff & AGM of Malay WD

LWUA Acting Administrator Lapus turning on the Water Pump